Federal Inspection Services (FIS) – General Aviation (GA) Facility
Status
The contractor is about 75% complete with construction. The building is nearly dried in with the last of the windows and exteriors being finished now. Exterior lighting is in progress and can be seen from Airport Drive pre-dawn and post-dusk. Exterior metal panels with the Tulsa International Airport lettering will start soon. The passenger boarding bridge is being set this week. Interiors are progressing well; a few interesting features are the wall of windows in the gate area, which provide an excellent view of the airfield; also, the bag claim carousel for international arrivals is in assembly; and terrazzo flooring is being installed. Construction is expected to be completed in February 2026 with operations expected to begin in Spring 2026.
Project Overview
Purpose
Provide screening of commercial passenger and general aviation flights arriving from outside the United States.